On-Going Project : Laguna Water

The Biñan Well Field Reservoir and Transmission Line Package 1 Project is composed of the following: erection of 4 – 5MLD steel bolted reservoir, construction of a pumping station that houses 4 – 5MLD Booster pumps, and a 5 km water distribution pipes.
The project aims to increase the water supply and service coverage of Laguna Water on the nearby area.
Contract details:
Start Date: April 28, 2015
End Date: July 20, 2016
Client: Laguna AAA Water Corporation